SR 177: Curve Realignment |
| |
|
|
| |
Description: |
The Arizona Department of Transportation is realigning a curve on State Route 177, about five miles south of Superior. The work will decrease the amount of the curve and enhance safety. |
| |
|
Improvements include:
- New culverts for drainage
- Extension of existing culverts
- Channel realignment
- Installation of guardrail and barbed wire fence
- Landscaping
|
| |
Expected Duration: |
The project is scheduled for completion in early summer 2011. |
| |
|
|
|
SR 260 Passing Lanes |
| |
Project No.: |
260 NA 317 H770501C HSIP-260-B-(202)A |
| |
Location: |
SR 260 Mileposts 317-318, 319-320, 330-331 |
| |
Contractor: |
Bison Contracting Co., Inc. |
| |
Programmed Cost: |
$3,071,215.55 |
| |
Scope: |
Construct three passing lanes one eastbound and two westbound |
| |
Expected Duration: |
Start Spring 2011 and complete Summer 2012 |
| |
|
|
|
US 60 Springerville to State Line |
| |
Project No.: |
060 AP 388 H766901C 060-F-(200)A |
| |
Location: |
US 60 Milepost 388-401 (Springerville to the state line) |
| |
Contractor: |
Hatch Construction & Paving, Inc. |
| |
Programmed Cost: |
$3,427,603,00 |
| |
Scope: |
Milling the existing asphaltic concrete pavement and replacing with new |
| |
Expected
Duration: |
Start June 2011 and complete Summer of 2012 |
| |
|
|