Safford District Projects
Senior Community Relations Officer: C.T. Revere 520.705.3574
More Safford District Projects
Safford Construction ORG 8430
US 70 Gila River Bridge at Bylas |
| |
|
Project No.: |
070 GH 291 H691001C |
| |
|
|
BR-STP 070-A(204)A |
| |
|
Location: |
Graham County on US 70 approximately 5 miles west of Bylas. Work begins at milepost 291.81 and extends easterly to milepost 293.74 for an approximate length of 1.9 miles. |
| |
|
Contractor: |
FNF Construction, Inc. |
| |
|
Awarded: |
November 18th, 2011 |
| |
|
Description: |
The work includes removing the existing twenty three-span steel girder bridge and replacing it with a fifteen-span precast prestressed concrete AASHTO.
Type VI girder bridge. In addition, the project includes roadway approach widening, intersection improvement, guardrail reconstruction, berm construction, irrigation line installation, pavement markings placement and other miscellaneous work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 380 working days. |
| |
|
|
|
US 70 at Reay Lane Intersection |
| |
|
Project No.: |
070 GH 335 HX23101C |
| |
|
|
STP-070-A(205)A |
| |
|
Location: |
Graham County on US 70 at mile post 335.6 within the Town of Thatcher |
| |
|
Contractor: |
C S Construction, Inc. |
| |
|
Awarded: |
September 16, 2011 |
| |
|
Description: |
The proposed work consists of installing a new traffic signal, sidewalk ramps, and other related items at the intersection of US 70 and Reay Lane. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 135 working days. |
| |
|
|
|
| |
|
|
|
US 191 Bowie Junction – Safford Highway Segment V |
| |
|
Project No.: |
191 GH 100 H818501C |
| |
|
|
STP-191-B(201)A |
| |
|
Location: |
Graham County on US 191 at milepost 100.59 to milepost 104.52, approximately 15 miles south of Safford |
| |
|
Contractor: |
CKC Construction & Materials LLC |
| |
|
Awarded: |
December 17, 2010 |
| |
|
Description: |
The work includes the construction of two new northbound lanes east of the existing roadway with asphaltic concrete and asphaltic rubber friction course; construction of turnouts and reconfiguring the “T” intersection with SR 266; extend five reinforced concrete box culverts; extend 13 existing pipe culverts; construct 14 new pipe culverts; construct 23 new lateral storm drains and catch basins; overlay the existing pavement with asphaltic concrete and asphaltic rubber friction course; erosion control; seeding; signing; pavement marking; and other related work. |
| |
|
Duration: |
The Department-Determined Construction Phase Time for substantial completion of the work shall be 500 calendar days. |
| |
|
|
|
US 191 Cold Creek Canyon Bridge #258 |
| |
|
Project No.: |
191 GE 154 H823102C |
| |
|
|
STP-191-C(212)A |
| |
|
Location: |
Greenlee County on US 191 at Milepost 154.9 approximately 10 miles south of the Town of Clifton |
| |
|
Contractor: |
Technology Construction, Inc. |
| |
|
Awarded: |
January 2012 |
| |
|
Description: |
The proposed work consists of removing the existing southbound Cold Creek Canyon bridge superstructure. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 15 working days. |
| |
|
|
|
US 191 Old Safford Road – Hill Street |
| |
|
Project No.: |
191 GE 159 H766501C |
| |
|
|
STP-191-C(209)A |
| |
|
Location: |
The project is located in Greenlee County on US 191, beginning at MP 159.70 and ending at MP 163.69 |
| |
|
Contractor: |
|
| |
|
Awarded: |
Bid Opening May 13, 2011 |
| |
|
Description: |
The work consists of milling and replacing with asphaltic concrete pavement and asphaltic concrete friction course, pavement markings, replacement of guardrail end terminals, shoulder build-up, seeding, installing loop detectors and other related work. |
| |
|
Duration: |
Time allowed for the completion of the work included in this project will be 100 working days. |
| |
|
|
|
| |
Benson Construction ORG 8431
City of Bisbee Arizona Street, Hazzard Street - Cole Avenue |
| |
|
Project No.: |
0000 CH BIS SL64201C BIS-0-(200)A |
| |
|
|
0000 CH BIS SS77501C BIS-0-(201)A |
| |
|
Location: |
Located in Cochise County in the City of Bisbee on Arizona Street beginning at Hazzard Street and extending 0.66 miles northeasterly to Cole Avenue. |
| |
|
Contractor: |
K E & G Construction, Inc. |
| |
|
Awarded: |
December 17, 2010 |
| |
|
Description: |
The proposed road work includes placement of aggregate base, asphaltic concrete, curb and gutter, a storm drain system, waterline replacement, signing, pavement markings, and other related work. The proposed enhancement work includes planting, irrigation, decorative walls and paving, bike bollards and street fixtures, pedestrian lighting, and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 145 working days. |
| |
|
|
|
City of Sierra Vista Avenida Cochise at Oakmont Drive |
| |
|
Project No.: |
0000 CH SVS SH45401C |
| |
|
|
HSIP-SVS-0(209)A |
| |
|
Location: |
City of Sierra Vista located in Cochise County |
| |
|
Contractor: |
K E & G Construction, Inc. |
| |
|
Awarded: |
October 21, 2011 |
| |
|
Description: |
The work consists of the installation of an eastbound right turn lane and a traffic signal at the intersection of Avenida Cochise at Oakmont Drive. The work also includes video detection, pre-emption sensors, and modifications to the existing signing, pavement markings, and medians. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 90 working days. |
| |
|
|
|
I-10 Mescal Road Traffic Interchange (TI) |
| |
|
Project No.: |
010 CH 297 H833601C / ER-010-E(211)A |
| |
|
Location: |
I-10 at Milepost 297.17 in Cochise County |
| |
|
Contractor: |
Vastco, Inc. |
| |
|
Description: |
The bridge rehabilitation project includes replacement of four columns at one pier, replacement of four pier caps, retrofit of abutments, installation of new precast, prestressed box beam girders, construction of the concrete deck, placement of approach slabs, painting of the existing and new portion of the bridge, pavement marking and other related work. |
| |
|
Duration: |
The time allowed for the completion of the work included in this project will be 130 calendar days. |
| |
|
|
|
I-10 & SR 90 Traffic Interchange (TI) |
| |
|
Project No.: |
010 CH 300H650401C |
| |
|
|
NH-STP-HSIP-TEA-010-E(200)N |
| |
|
Location: |
Cochise County on I-10 at the State Route 90 Traffic Interchange near the City of Benson |
| |
|
Contractor: |
Borderland Construction Co., Inc. |
| |
|
Awarded: |
September 1, 2010 |
| |
|
Description:
Project Web site |
The project will reconstruct the I-10/SR 90 TI overpass structures, SR 90 below the overpass, entrance and exit ramps in both directions, realign and reconstruct I-10 mainline west of the TI, construct three access roads (W. Dark Star Road, N. Vidal Trail and W. Calvary Lane), drainage improvements, lighting, utility relocations, signing and marking, and other related work. |
| |
|
Duration: |
The time allowed for the completion of the project is 500 working days. |
| |
|
|
|
SR 92 MP 347 Bridge #199 Scour Retrofit |
| |
|
Project No.: |
092 CH 346 H799601C |
| |
|
|
STP-092-A(201)A |
| |
|
Location: |
Cochise County on State Route 92, 10 miles west of Bisbee |
| |
|
Contractor: |
K.A.Z. Construction, Inc. |
| |
|
Awarded: |
April 2012 |
| |
|
Description: |
The work consists of constructing scour protection concrete floors under existing bridge #199, construction of cut-off walls, shotcrete, bank protection and other related work. |
| |
|
Duration: |
Time allowed for the completion of work included in this project will be 65 working days |
| |
|
|
|
SR 90 Whetstone Ti - Jct Sr 80 Middle Canyon Wash Bridge SB |
| |
|
Project No.: |
090 CH 299 H799401C |
| |
|
|
090-A-(203)A |
| |
|
Location: |
Cochise County on State Route 90 north of Huachuca City at Milepost 299.86 |
| |
|
Contractor: |
K.A.Z. Construction, Inc |
| |
|
Awarded: |
February 2012 |
| |
|
Description: |
The work consists of constructing concrete floors underneath the south-bound existing bridge (Structure #698) and other related work. |
| |
|
Duration: |
Time allowed for the completion of this project will be 80 working days. |
| |
|
|
|
| |
|