Current Flagstaff Projects

For more project information and updates, please visit ADOT News page.

I-40 Pavement Preservation through Flagstaff
  Project No.: 40 CN 190 H7958 01C
  Location:

Project is located on eastbound and westbound lanes of I-40 between Riordan Railroad Overpass (MP 190) and Country Club TI (MP 201) through Flagstaff.

  Contractor: Markham Contracting Co., Inc.
  Programmed Cost: $3,750,000
  Scope:

Remove existing asphalt and replace with a layer of rubberized asphalt along I-40 as well as on- and off- ramps.

  Expected Project
Duration:
The project began on Monday, July 12 and is expected to be complete by late August 2010.
  Project Notes:
I-40 will be reduced to one lane in each direction allowing for a safe work zone for motorists and crews to safely work.  In addition, on- and off-ramps will be intermittently closed.  Please check back later for more specific information regarding interstate ramp closures.
  Project Hotline:

1.877.497.5203

  Traffic Alert:

August 12, 2010 - I-40 Paving Update

 

I-40 Walnut Canyon Westbound

  Project No.: 40 CN 205 H545701C ARRA-040-E(202)A
  Location:

Project is westbound only from MP 209.1 to MP 205.1. The Cosnino Interchange is located within this project.

  Contractor: C.S.&W. Contractors, Inc.
  Programmed Cost: $5,809,917.48
  Scope:

Reprofile the vertical curves. This involves taking out some of the small grades.

  Expected Project
Duration:
Project will run into the fall of 2009 at which time it will stop. It will be resumed and completed Spring 2010.
  Project Update:

I-40 roadwork at Cosnino Road ~ June 16, 2010

     
Lake Mary Road – Stoneman lake Road to Happy Jack Ranger Station
  Project No.:

SS76401C

  Location:

Lake Mary Road between Stoneman Lake Road and Happy Jack Ranger Station (mile post 307.5 to mile post 310).

  Contractor: Intermountain West Civil Constructors.
  Programmed Cost:

$ 606,955

  Scope: A local government (Coconino County) ARRA project.  Remove and replace asphalt.
  Expected Project
Duration:

The project began August 16 and is expected to be complete by late August 2010.

  Project Notes:
Construction will occur between 6:00 a.m. and 6:00 p.m. week days, as well as weekends. The work should be completed by Sunday, August 29, weather permitting. The project will include asphalt paving with a new friction course overlay, which will provide better traction and reduce traffic noise.
  Contact:

ldaley@coconino.az.gov Public Information Coordinator for Coconino County Public Works, Lindsay Daley

  News Release: Paving Project to Begin on Portion of Lake Mary Road
August 11, 2010
     
McGuireville Rest Area – Yavapai County Line S/B
  Project No.: 017-YV 296 H613601C IM-017-B(008)A
  Location:
McGuireville Rest Area, and the south bound lanes from the Yavapai County Line to the rest area.
  Contractor: Fisher Sand & Gravel Co. dba Southwest Asphalt Paving
  Programmed Cost: $6,333,333
  Scope:
Make waste water system improvements at the McGuireville rest area; mill and replace the existing asphalt and apply friction course from the county line to the rest area.
  Expected Project
Duration:

Fall 2009 to Summer 2010

  Traffic Alert:

July 29, 2010 - Crews start work earlier to avoid monsoon rains

     
SR 89A Continuous Highway Lighting
  Project No.: 89A YV 371 H7130 01D, HES A89-B(202)
  Location: SR 89A from milepost 371 to 373
  Contractor: Not bid yet
  Programmed Cost: Current estimate $2,000,000
  Scope: Install continuous highway lighting and traffic signal at Andante.
  Expected Project Duration: Projected for Fall 2010 to Spring 2011
  Project Documents: Sedona Pedestrian Crossing Study
    Highway Enhancements for Safety Report
    Funding Approval
    Revised Funding Approval
    Final Project Assessment
    Final Lighting Design Criteria Report
    Presentation to Sedona City Council October 28, 2009
    Public Information Packet on Lighting System Alternatives
    Public Comment Form
    Information on Nighttime Lighting
    Final Pedestrian Crosswalk Study
    Final Pedestrian Crosswalk Study Appendix
    Final Lighting Design Type Report
    Public Involvement Summary
     
SR 179 Village of Oak Creek to Y (Project 1 and 2)
  Project No.: STP-TEA-A(001)B and STP-TEA-A(002)B
  Location:
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona.
  Contractor: Southwest Asphalt Paving (Project 1)
  Programmed Cost: Project 1 $36,114,000
Project 2 $51,750,000
  Scope:
Projects consist of complete rebuild of highway to a multimodal, two lane parkway.
  Expected Project Duration: Project 1 Completed
Project 2 Spring 2008 to Spring 2010
     

Documents are posted as they become available in PDF format, which requires Adobe Reader to view.