| I-40 Pavement Preservation through Flagstaff |
| |
Project No.: |
40 CN 190 H7958 01C |
| |
Location: |
Project is located on eastbound and westbound lanes of I-40 between Riordan Railroad Overpass (MP 190) and Country Club TI (MP 201) through Flagstaff. |
| |
Contractor: |
Markham Contracting Co., Inc. |
| |
Programmed Cost: |
$3,750,000 |
| |
Scope: |
Remove existing asphalt and replace with a layer of rubberized asphalt along I-40 as well as on- and off- ramps. |
| |
Expected Project
Duration: |
The project began on Monday, July 12 and is expected to be complete by late August 2010. |
| |
Project Notes: |
I-40 will be reduced to one lane in each direction allowing for a safe work zone for motorists and crews to safely work. In addition, on- and off-ramps will be intermittently closed. Please check back later for more specific information regarding interstate ramp closures. |
| |
Project Hotline: |
1.877.497.5203 |
| |
Traffic Alert: |
August 12, 2010 - I-40 Paving Update |
| |
I-40 Walnut Canyon Westbound |
| |
Project No.: |
40 CN 205 H545701C ARRA-040-E(202)A |
| |
Location: |
Project is westbound only from MP 209.1 to MP 205.1. The Cosnino Interchange is located within this project. |
| |
Contractor: |
C.S.&W. Contractors, Inc. |
| |
Programmed Cost: |
$5,809,917.48 |
| |
Scope: |
Reprofile the vertical curves. This involves taking out some of the small grades. |
| |
Expected Project
Duration: |
Project will run into the fall of 2009 at which time it will stop. It will be resumed and completed Spring 2010. |
| |
Project Update: |
I-40 roadwork at Cosnino Road ~ June 16, 2010 |
| |
|
|
| Lake Mary Road – Stoneman lake Road to Happy Jack Ranger Station |
| |
Project No.: |
SS76401C |
| |
Location: |
Lake Mary Road between Stoneman Lake Road and Happy Jack Ranger Station (mile post 307.5 to mile post 310). |
| |
Contractor: |
Intermountain West Civil Constructors. |
| |
Programmed Cost: |
$ 606,955 |
| |
Scope: |
A local government (Coconino County) ARRA project. Remove and replace asphalt. |
| |
Expected Project
Duration: |
The project began August 16 and is expected to be complete by late August 2010. |
| |
Project Notes: |
Construction will occur between 6:00 a.m. and 6:00 p.m. week days, as well as weekends. The work should be completed by Sunday, August 29, weather permitting. The project will include asphalt paving with a new friction course overlay, which will provide better traction and reduce traffic noise. |
| |
Contact: |
ldaley@coconino.az.gov Public Information Coordinator for Coconino County Public Works, Lindsay Daley |
| |
News Release: |
Paving Project to Begin on Portion of Lake Mary Road
August 11, 2010 |
| |
|
|
| McGuireville Rest Area – Yavapai County Line S/B |
| |
Project No.: |
017-YV 296 H613601C IM-017-B(008)A |
| |
Location: |
McGuireville Rest Area, and the south bound lanes from the Yavapai County Line to the rest area. |
| |
Contractor: |
Fisher Sand & Gravel Co. dba Southwest Asphalt Paving |
| |
Programmed Cost: |
$6,333,333 |
| |
Scope: |
Make waste water system improvements at the McGuireville rest area; mill and replace the existing asphalt and apply friction course from the county line to the rest area. |
| |
Expected Project
Duration: |
Fall 2009 to Summer 2010 |
| |
Traffic Alert: |
July 29, 2010 - Crews start work earlier to avoid monsoon rains |
| |
|
|
| SR 89A Continuous Highway Lighting |
| |
Project No.: |
89A YV 371 H7130 01D, HES A89-B(202) |
| |
Location: |
SR 89A from milepost 371 to 373 |
| |
Contractor: |
Not bid yet |
| |
Programmed Cost: |
Current estimate $2,000,000 |
| |
Scope: |
Install continuous highway lighting and traffic signal at Andante. |
| |
Expected Project Duration: |
Projected for Fall 2010 to Spring 2011 |
| |
Project Documents: |
Sedona Pedestrian Crossing Study |
| |
|
Highway Enhancements for Safety Report |
| |
|
Funding Approval |
| |
|
Revised Funding Approval |
| |
|
Final Project Assessment |
| |
|
Final Lighting Design Criteria Report |
| |
|
Presentation to Sedona City Council October 28, 2009 |
| |
|
Public Information Packet on Lighting System Alternatives |
| |
|
Public Comment Form |
| |
|
Information on Nighttime Lighting |
| |
|
Final Pedestrian Crosswalk Study |
| |
|
Final Pedestrian Crosswalk Study Appendix |
| |
|
Final Lighting Design Type Report |
| |
|
Public Involvement Summary |
| |
|
|
| SR 179 Village of Oak Creek to Y (Project 1 and 2) |
| |
Project No.: |
STP-TEA-A(001)B and STP-TEA-A(002)B |
| |
Location: |
Project 1 is from MP 304.5 (1 mile south of Village of Oak Creek) to MP 310.4 (Back o’ Beyond) and
Project 2 is from MP 310.4 to 313.4 (the “Y”) in the City of Sedona. |
| |
Contractor: |
Southwest Asphalt Paving (Project 1) |
| |
Programmed Cost: |
Project 1 $36,114,000
Project 2 $51,750,000 |
| |
Scope: |
Projects consist of complete rebuild of highway to a multimodal, two lane parkway. |
| |
Expected Project Duration: |
Project 1 Completed
Project 2 Spring 2008 to Spring 2010 |
| |
|
|